The boiler fuel feeding system at the plant is still operated manually, requiring significant manpower and limiting boiler availability during peak production periods. This situation reduces operational efficiency and increases the risk of delays in fuel supply to the boilers, which can affect the continuity of the production process.
Carry out the turnkey construction of a moving floor station system, including civil works, building construction, mechanical systems, and supporting conveyors. The project must result in an automated, reliable fuel supply system capable of supporting the operational needs of boilers with higher capacity.
Our team handles all aspects of the project in an integrated manner, from civil foundation work and building construction to the installation of the mechanical moving floor system and the conveyor connecting to the boiler area. All phases of the work are coordinated within a single integrated project and culminate in a comprehensive commissioning process to ensure the system operates as designed.